Jun 2008 - Progress on site
The Quedgeley scheme seems to be progressing slightly faster than Brockworth which began in January of this year, but this is predominantly due to the timber frame structure which was delivered to site and unloaded by the tower crane on Monday 9 June. Phase one of the structure will be completed by the end of July.
Scoffolding in place ready for the timber frames
Unloading the frames only took a few hours and thank goodness the weather was good!